How connection works: the common steps
- Availability Find out whether there is a water main in the street and whether there is a branch up to the plot boundary. In Riga, this is shown by the Rīgas ūdens (Riga's water utility) “Service availability” form and vaitevtovajag.lv, in Mārupe municipality by the MKP network map, and in Sigulda municipality by the Saltavots network map.
- Technical conditions Submit an application to the water utility with the property documents, the boundary plan and the planned consumption. In most municipalities technical conditions are issued free of charge, but they can be refused while there is an unpaid debt for services.
- Design A certified designer prepares the service pipe design, which is filed with the municipal building authority (būvvalde) with an explanatory memorandum (paskaidrojuma raksts) or, in a simple case, a notification. It is built by a construction company or a certified specialist under the supervision of the water utility.
- Handover The owner submits an as-built survey plan, and the utility fits and seals the meter. In several municipalities, you have to confirm in writing that the local well, borehole or spike well (“spice” in Latvian) is not connected to the mains network.
- Contract The utility signs a service contract, and the water supply starts.
Source: Cabinet Regulation No. 253 of 09.05.2017 “Construction Regulations for Certain Engineering Structures”, sub-point 2 of point 6² and point 18; Cabinet Regulation No. 500 (General Construction Regulations), sub-point 3.1.31 of Annex 1; municipal binding regulations in the tables below. Sources: likumi.lv, water utility websites; checked 03.11.2026.
Riga: Rīgas ūdens
At the end of 2025, mains water was available to 98.04% of Riga's residents. Still without it are Dārziņi, Trīsciems (water main only on Jaunciema gatve) and Mangaļsala, where a local system operates. In many other neighbourhoods, individual streets lack a water main or sewerage.
Rīgas ūdens prepares technical conditions within 11 working days free of charge, if there are no debts. Rīgas ūdens does not design or build private connections itself: the owner chooses the designer and the builder. If the network in the street has to be built or rebuilt, Rīgas ūdens organises the work at the applicant's expense under a connection agreement. The water tariff is €1.41/m³ excluding VAT (September 2026).
There is no co-financing for water mains in Riga. Rīgas ūdens states it directly: “No co-financing is provided for water supply system connections.” The earlier programme, which also covered water mains, ceased to apply on 01.04.2026.
Riga's rules do not require existing houses with their own well to connect; for new buildings it is mandatory if there is a network and a branch up to the plot boundary. The water situation in the city: Riga.
Source: Rīgas ūdens contract performance report for 2025; rigasudens.lv pages “Property without a connection”, “Service connection” and “Municipal co-financing for Cohesion Fund projects”; Riga City Council binding regulations No. 17 (2017), points 5, 8, 12–16 and 63.6; Riga City Council binding regulations No. 67 (2018). Sources: rigasudens.lv, likumi.lv; checked 03.11.2026.
The Riga region: water utilities and technical conditions
| Place | Water utility | Technical conditions | What to know |
|---|---|---|---|
| Mārupe | Mārupes komunālie pakalpojumi | free of charge, valid for 1 year | all connection costs are paid by the owner |
| Ķekava, Baldone, Baloži | Ķekavas nami (Rīgas ūdens in part of the territory) | valid for 2 years | you must confirm that the borehole or spike well is not connected to the network; the meter is paid for by the utility |
| Olaine | Olaines ūdens un siltums | valid for 2 years | the service pipe from the property is built and paid for by the user |
| Salaspils | Valgums-S | free of charge, within a month | excavation permit from the Salaspils building authority |
| Ādaži | Ādažu ūdens | free of charge, within 20 working days | a new connection may carry a one-off capacity fee |
| Sigulda | Saltavots | free of charge, within 11 working days, valid for 2 years | the branch up to the plot boundary is built by the utility |
| Jūrmala | Jūrmalas ūdens | free of charge, within 10 working days, valid for 2 years | connection at the owner's expense |
| Ogre, Ikšķile, Ķegums | Ogres komunikācijas, Ikšķiles māja, Ķeguma Stars | in Ogre free of charge, valid for 2 years | the service pipe in the street is built by a licensed construction company |
| Vangaži | Ropaži municipality's own utility | valid for 2 years | a new building without a branch needs a building permit |
| Saulkrasti | Saulkrastu komunālserviss | within a month, valid for 1 year | free of charge if no outline scheme has to be drawn |
| Iecava | Bauskas novada komunālserviss | valid for 2 years | for existing buildings next to a street network, connection was mandatory by 31.12.2025 |
| Jelgava | Jelgavas ūdens | valid for 2 years | the design must be agreed with the utility |
Source: the binding regulations of the respective municipalities on water management services (Mārupe 11/2023, Ķekava 21/2022, Olaine SN4/2018, Ādaži 72/2022, Sigulda 18, Jūrmala 38, Ogre 24/2025, Ropaži 21/22, Saulkrasti 5/2022, Bauska 5, Jelgava 19-10) and the water utilities' websites. Sources: likumi.lv; checked 03.11.2026.
Co-financing for a water main connection
| Municipality | Amount for the water main | Conditions and dates |
|---|---|---|
| Riga | none | Rīgas ūdens: no co-financing is provided for water supply connections |
| Mārupe municipality | €30/m, up to €1,500; for priority groups €50/m, up to €2,000 | binding regulations No. 16/2025, in force from 03.06.2025; connection built after 01.07.2022; registered as resident at the property for at least a year; paid out after construction |
| Ķekava municipality | up to 100%, up to €2,500 (for water main and/or sewerage) | binding regulations No. 14/2023, version from 06.03.2026; priority groups only; applications within 60 days of the competition being announced |
| Ropaži municipality | 50%, up to €2,000 and €60/m; for priority groups 100%, up to €8,000 and €120/m | binding regulations No. 34/23, in force from 01.01.2024; registered as resident for at least 6 months; work within 6 months of the contract |
| Sigulda municipality | up to 50% (€60/m); for priority groups up to 100% (€120/m); in total up to €2,500 | binding regulations No. 17 (2024), in force from 31.05.2024; application by 1 November for the next year's budget, for 2028 by 01.11.2027; connections already built are not funded |
| Saulkrasti municipality | 100%, up to €3,500 including VAT (for water main or sewerage) | binding regulations No. 5/2026, in force from 22.05.2026 to 01.01.2027; only for needy and low-income households; networks must be presented by 20.11.2026, payments by 31.12.2026 |
| Jelgava | for street networks: the municipality up to 70%, the group of residents at least 30% | binding regulations No. 26-4, in force from 17.03.2026; applications every year by 10 March |
| Ogre and Ādaži municipalities | none | co-financing cancelled in 2022 |
| Olaine and Salaspils municipalities, Jūrmala, Iecava | not found | in Iecava (Bauska municipality), only sewerage is co-financed |
Priority groups differ between municipalities, but they are usually needy and low-income persons, large families, persons with disabilities and single pensioners. In most municipalities the owner must be registered as resident at the property and have no tax debts, and the money is granted within the annual budget. Before the work, check the current version on likumi.lv, because the rules change.
Source: binding regulations on co-financing (Mārupe 16/2025, Ķekava 14/2023 and 3/2026, Ropaži 34/23, Sigulda 17, Saulkrasti 5/2026, Jelgava 26-4, Ogre 9/2022, Ādaži 24/2022, Bauska 4/2024) and the Rīgas ūdens page on co-financing. Sources: likumi.lv, rigasudens.lv; checked 03.11.2026.
When your own well or borehole is the wiser choice
- There is no water main in the street and there will not be one in the coming years. In Dārziņi, a feasibility study is running from 2025 to 2027, and the chair of a Riga City Council committee has said that implementation may take until 2039.
- The trunk main is far away, and you would have to pay for building the street network yourself.
- You need water for watering the garden: your own spike well provides it without a tariff per cubic metre, while the house stays on city water.
Connecting makes sense if the trunk main already runs past the plot: you do not have to look after a pump, filters and testing, and the utility controls the water quality. The costs of your own source are a spike well from €350 or a ~30 m borehole from €2,000 without the pump, plus the pump, electricity and, if the tests show it is needed, water treatment.
Tariffs for comparison (excluding VAT): Rīgas ūdens €1.41/m³, Ādažu ūdens €1.42/m³, Ķekavas nami €1.09/m³, Mārupes komunālie pakalpojumi €0.78/m³, Valgums-S €1.66/m³ (from 01.10.2026). If you choose your own source, we build the whole system, from the source to the tap: water supply system for a private house.
Source: Rīgas ūdens on the Dārziņi project and the tariff; Ķekavas nami tariff notice (tariff from 01.01.2026); MKP single tariff from 01.07.2026; Public Utilities Commission (SPRK) decision No. 56 (Ādažu ūdens, from 01.09.2026); SPRK decision No. 67 (Valgums-S, from 01.10.2026). Sources: rigasudens.lv, kekavasnami.lv, likumi.lv, adazuudens.lv; checked 03.11.2026.
Can you keep your own well after connecting
Yes, but as a separate system. In Riga it is prohibited to connect the network of a local water source, such as a borehole, to the mains water supply, including through the inlet or the house's internal network, and the fine is up to 28 fine units (€140). In Ķekava municipality, Jūrmala and Bauska municipality, if a building has both sources, the connection needs an air gap of at least 50 mm or a special non-return valve. In Ogre and Ropaži municipalities, the two sources must not be used at the same time.
A spike well or a well for garden watering can be kept if it is not connected to the house's water pipes. If you will no longer use a borehole, it is decommissioned so that surface water does not get through it into the deeper layer: borehole decommissioning.
Source: Riga City Council binding regulations No. 17, points 63.6 and 97; Ķekava municipality binding regulations No. 21/2022, points 14.3, 23 and 58; Jūrmala binding regulations No. 38, points 13.3 and 22; Bauska municipality binding regulations No. 5, point 10; Ogre municipality binding regulations No. 24/2025, point 12; Ropaži municipality binding regulations No. 21/22, Section 17; Cabinet Regulation No. 696, point 21. Available at: likumi.lv; checked 03.11.2026.
Sources
- Riga: 98.04% availability; Dārziņi, Trīsciems, Mangaļsala without mains water; binding regulations No. 67 ceased to apply on 01.04.2026 checked 3 November 2026
- Rīgas ūdens technical conditions within 11 working days, free of charge checked 3 November 2026
- Rīgas ūdens service availability form checked 3 November 2026
- In Riga, no co-financing is provided for water supply connections checked 3 November 2026
- Riga binding regulations No. 17: connection mandatory for new buildings (point 5), design (point 8), street network at the applicant's expense (points 12–16), prohibition on connecting a borehole (point 63.6), fine (point 97) checked 3 November 2026
- Riga binding regulations No. 67 (water + sewerage, 60%) checked 3 November 2026
- vaitevtovajag.lv address tool; tariff €1.41/m³ excluding VAT (Sept. 2026) checked 3 November 2026
- Dārziņi feasibility study 2025–2027, possible implementation by 2039 checked 3 November 2026
- Mārupe binding regulations No. 11/2023: technical conditions free of charge, 1 year, costs paid by the owner checked 3 November 2026
- Mārupe binding regulations No. 16/2025: for the water main €30/m up to €1,500, for priority groups €50/m up to €2,000 checked 3 November 2026
- MKP network map; single tariff €0.78/m³ from 01.07.2026 checked 3 November 2026
- Ķekava binding regulations No. 21/2022: technical conditions 2 years, confirmation about the borehole or spike well, air gap checked 3 November 2026
- Ķekava binding regulations No. 14/2023: up to 100%, up to €2,500, priority groups checked 3 November 2026
- Ķekavas nami procedure and tariff €1.09/m³ from 01.01.2026 checked 3 November 2026
- Olaine binding regulations SN4/2018: technical conditions 2 years, service pipe by the user checked 3 November 2026
- Valgums-S: technical conditions free of charge within a month, excavation permit checked 3 November 2026
- Valgums-S tariff €1.66/m³ from 01.10.2026 (SPRK decision No. 67) checked 3 November 2026
- Ādaži binding regulations No. 72/2022: technical conditions within 20 working days, capacity fee, obligation to connect within 1 year (point 15) checked 3 November 2026
- Ādažu ūdens tariff €1.42/m³ from 01.09.2026 checked 3 November 2026
- Ādaži binding regulations No. 24/2022 cancel the Carnikava co-financing checked 3 November 2026
- Saltavots: technical conditions within 11 working days, free of charge, 2 years checked 3 November 2026
- Sigulda binding regulations No. 18 (2022): branches up to the boundary at the utility's expense (point 19.6) checked 3 November 2026
- Sigulda binding regulations No. 17 (2024): 50%/€60/m, 100%/€120/m, up to €2,500, application by 1 November checked 3 November 2026
- Jūrmalas ūdens: technical conditions within 10 working days, free of charge, 2 years checked 3 November 2026
- Jūrmala binding regulations No. 38 (2024): costs for the owner, confirmation about the borehole or spike well, air gap checked 3 November 2026
- Ogres komunikācijas: technical conditions free of charge, 2 years checked 3 November 2026
- Ogre binding regulations No. 24/2025: the two sources must not be used at the same time (point 12) checked 3 November 2026
- Ogre binding regulations No. 9/2022 cancel the co-financing rules checked 3 November 2026
- Ropaži binding regulations No. 21/22: technical conditions 2 years, building permit, Section 17 checked 3 November 2026
- Ropaži binding regulations No. 34/23: 50% up to €2,000, for priority groups 100% up to €8,000 checked 3 November 2026
- Saulkrasti binding regulations No. 5/2022: technical conditions within a month, 1 year checked 3 November 2026
- Saulkrasti binding regulations No. 5/2026: 100% up to €3,500, for needy and low-income households, by 20.11.2026 and 31.12.2026 checked 3 November 2026
- Bauska binding regulations No. 5/2024: technical conditions 2 years, mandatory connection by 31.12.2025, point 10 air gap checked 3 November 2026
- Bauska binding regulations No. 4/2024: co-financing for sewerage only checked 3 November 2026
- Jelgava binding regulations No. 19-10: technical conditions 2 years, design to be agreed checked 3 November 2026
- Jelgava binding regulations No. 26-4: residents' share 30/70, applications by 10 March checked 3 November 2026
- Cabinet Regulation No. 253: explanatory memorandum or notification for a service pipe (point 18) checked 3 November 2026